The First Ride of Your Disney Vacation Just Got a $253 Million Upgrade at Orlando International Airport
Orlando International Airport, better known as MCO, opened upgraded Gate Link tram service to Gates 100-129 on Thursday, October 1.
New vehicles. Modernized track. Each set carries up to 240 passengers.
It is the first milestone in a $253 million project, itself part of MCO’s $6.9 billion Capital Improvement Program.
What Is Done and What Is Not
One of two tracks serving Gates 100-129 is finished. Crews are working on the second now. Three new trams were installed on February 27 and have been in testing since. Lance Lyttle, CEO of the Greater Orlando Aviation Authority, called the result “a smoother, more dependable experience for passengers.”The Upgrade Worth Knowing About
Platform screen doors. They are the glass barriers between the platform edge and the vehicle, opening only when a tram arrives. Three benefits. Nobody can fall or step onto the guideway, which is the main safety risk in automated transit. Conditioned air stays in the station instead of escaping into Florida. And dwell times get more consistent, because the system is not waiting on unpredictable boarding. The project also covers new running surfaces, power distribution, vehicle controls, communications, and operating systems. MCO cites reliability, capacity, modern safety controls, and energy efficiency as goals.🚆✨ That new Gate Link smell! ✨🚆 A brand-new Gate Link tram is now in service, transporting travelers to and from Gates 100-129. This is the first of four scheduled tram replacements as part of the Gate Link Replacement Project for Airsides 2 and 4, serving Gates 70-129. pic.twitter.com/pU0a0uO7E0
— Orlando International Airport (@MCO) October 1, 2026
Why They Needed It
Gates 100-129 are on Airside 2, where the original system went in during 2000. Gates 70-99 are on Airside 4, dating to 1990, with vehicles replaced in 2008. That is 18-year-old equipment on a 36-year-old guideway. Both run as dual-lane shuttles, roughly 2,000 feet per lane. Trip time is one minute and thirty seconds, with 40 seconds of dwell at each station. Notable: the oldest system is scheduled last. A 2017 project already replaced the systems serving Gates 1-29 and Gates 30-59. The Aviation Authority board approved the current funding in October 2023, with Mitsubishi Heavy Industries America holding the design, build, operate, and maintain contract.The Schedule
- Gate Link 4800, Gates 100-129: December 3, 2025, to July 2026
- Gate Link 4700, Gates 100-129: July 2026 to December 2026
- Gate Link 4600, Gates 70-99: December 2026 to June 2027
- Gate Link 4500, Gates 70-99: June 2027 to October 2027